Crane Outrigger Pad Size: Working Out Ground Pressure Before the Lift
In this article
A truck-mounted crane arrives to lift precast stair flights into a building. The only level spot is a strip of ground beside the basement wall, backfilled two months earlier. The outriggers go down on their standard floats, the operator levels the machine, and the first lift goes up. On the second slew, one float starts to push into the fill. The crane is lifting well inside its load chart. The ground under it is not.
Choosing the crane outrigger pad size is the part of a lift that site teams most often leave to the operator on the day. It shouldn't be. The load chart only holds if the ground can carry what the outriggers put into it, and checking that takes a short calculation and three pieces of information you can collect before the crane is booked.
This guide covers the arithmetic, where each number comes from, who is responsible for the ground, and the Egyptian site conditions that catch people out. It draws on the US crane rule on ground conditions, OSHA 29 CFR 1926.1402, and the UK Construction Plant-hire Association's guide to supplying and operating mobile cranes, CPA CIG 2308. Both are foreign references, not Egyptian law, but they set out the division of work clearly.
Why the load chart assumes good ground
Every figure on a crane's load chart assumes the machine is level and fully supported. OSHA 1926.1402 puts it plainly: a crane may not be assembled or used unless the ground is firm, drained and graded enough that, with mats or blocking where needed, the manufacturer's requirements for support and level are met.
If one outrigger sinks, the crane tilts. A small tilt moves the load further out, the radius grows, and the capacity at that radius falls. That is how a lift that was well inside the chart becomes an overturn. How the chart itself works is covered in how to read a crane load chart. This article is about the other half: the ground.
Ground pressure: one division
The pressure an outrigger puts into the ground is the load on it divided by the area that carries it:
ground pressure = outrigger load ÷ pad area
Work in kilonewtons and square metres and the answer comes out in kN/m² (the same as kPa). Many Egyptian soil reports and engineers quote bearing capacity in kg/cm². One kg/cm² is about 98 kN/m², so divide kN/m² by 98 to compare.
Here is a worked example. The figures are illustrative, not the outrigger load of any particular crane. Say the heaviest outrigger load for the lift is 30 tonnes, about 294 kN:
| What is under the outrigger | Area | Ground pressure |
|---|---|---|
| Standard float only, 0.5 × 0.5 m | 0.25 m² | about 1,177 kN/m² (about 12 kg/cm²) |
| Mat 1.2 × 1.2 m | 1.44 m² | about 204 kN/m² (about 2.1 kg/cm²) |
| Mat 2.0 × 2.0 m | 4.0 m² | about 74 kN/m² (about 0.75 kg/cm²) |
The load is the same in all three rows. Only the area changes, and the pressure falls by a factor of sixteen between the first row and the last.
To size a mat, turn the division around: required area = outrigger load ÷ allowable ground pressure. If the soil report allows, say, 100 kN/m² at the set-up point, the same 294 kN needs at least 2.94 m², so a square mat of at least 1.75 × 1.75 m. Add the weight of the mat itself and round up, never down.
Two cautions. First, a mat only spreads the load across its full area if it is stiff enough. A thin plate under a small float bends, and the area that actually carries the load is smaller than the plate. The mat's rated capacity comes from its maker. Second, the allowable ground pressure must come from someone qualified to give it. This article does not give typical values for soil types, and nor should a site team guess them.
Where the outrigger load comes from
The load on each outrigger is not a quarter of the crane's weight plus the load. As the boom slews, the weight shifts, and when the boom is over one outrigger, that outrigger takes far more than its share. The load also changes with counterweight, outrigger extension, boom length and radius.
So the number has to come from the crane. CPA CIG 2308 says the crane supplier should provide accurate loadings from the crane, and it lists what the supply information should include:
- Outrigger maximum point loads for a full 360° slew while rigging (maximum counterweight, minimum boom, minimum radius) and for every planned lift.
- The source of those figures, such as the manufacturer's printout or digital output.
- The outrigger mats that come with the crane: material, dimensions, capacity and the weight of each mat.
- Outrigger width and spacing, and whether the crane can set its outriggers asymmetrically.
Most crane manufacturers provide software or tables that give these loads for a given configuration. Ask for the printout for your lift, not a general figure for the machine.
Who is responsible for the ground
This is the point that surprises site teams most. Under CPA CIG 2308, responsibility for assessing and preparing the ground stays with the crane user, whichever type of hire contract is chosen. The supplier provides the loads; the user establishes what the ground, structure or services beneath can carry. The appointed person can then ask the supplier for larger pads to bring the pressure down to an acceptable level.
OSHA 1926.1402 puts a similar duty on the controlling entity, usually the main contractor. It must ensure the ground is prepared, and tell the crane user and operator about hazards beneath the set-up area, such as voids, tanks and utilities, wherever they appear in its drawings or soil reports or are otherwise known. If the operator finds the ground unsuitable, the two sides must agree on the preparation needed before work goes on.
In Egypt, the contract and the lift plan should say the same thing. If nobody on site owns the ground question, the operator ends up answering it with a glance on the morning of the lift. Who signs off the lift plan is set out in the UK HSE guidance on planning lifting operations, cited below.
Egyptian site conditions to watch
- Backfill beside basements and foundations. Recently placed fill, especially in a narrow strip beside a wall, may not have been compacted to carry a point load. It is one of the most common set-up spots on a tight plot, and one of the worst.
- Septic tanks, underground water tanks and chambers. Common on villa plots and in older areas, and often missing from drawings. Ask the owner and look for covers before choosing the set-up point.
- Buried cables and pipes in the pavement. Reinstated trenches are softer than the ground around them.
- Loose sand. New cities and desert sites often have a loose surface layer over firmer ground. A float can bed in as the crane slews.
- Wet ground after rain. On the North Coast and in Alexandria during winter, a set-up that was firm last week may not be today. OSHA's word is drained, not just firm.
- Slabs, podiums and ramps. A crane standing on any structure needs a structural engineer's check, whatever the mat size.
- Edges of excavations. Keep outriggers back from the edge of a dig. The safe distance depends on the soil and the depth, and the person who designed the excavation should set it.
Setting the mats on the day
- Put the mat on prepared, level ground, with full contact and no voids underneath. Remove loose material first.
- Centre the float on the mat. A float near one edge loads only part of the mat.
- Use mats rated for the job. CPA says outrigger mats should be of proprietary design and quality, not a stack of scrap timber or a kerbstone.
- Plan how the mats get placed. Large mats are heavy and may need the crane or another machine to set them, which CPA flags as a manual-handling issue.
- Watch the floats during the first slew, and stop if anything settles.
The same thinking applies to any machine that stands on stabilisers: a telehandler with its stabilisers down, or a truck-mounted access platform. If you are weighing a telehandler against a small crane, the comparison is in telehandler vs crane.
What to send with the crane request
To get a crane and mats sized for your ground, send:
- The load, its weight, and the lift radius.
- Photos of the proposed set-up point and the ground surface.
- The allowable ground bearing pressure from the soil report or your engineer, in kN/m² or kg/cm², or "not known".
- Any known underground tanks, chambers, cables or basements near the set-up point.
- Whether the crane will stand on a slab, ramp or backfill.
Then ask for the maximum outrigger load for your configuration and the size and capacity of the mats that come with the crane. The rest of the request, load and radius, is covered in how to choose a crane for your lift. If there are overhead lines near the set-up point, check the safe distance from power lines at the same site visit.
Quick summary
- The load chart assumes firm, level ground. If an outrigger sinks, the capacity goes.
- Ground pressure = outrigger load ÷ pad area. Bigger, stiffer mats bring it down.
- Take the outrigger load from the crane supplier, for your configuration and a full slew.
- Take the allowable ground pressure from a soil report or an engineer, never a guess.
- The ground stays the user's responsibility. Look for backfill, tanks, services and slabs.
- Size the mat with a margin, place it level and centred, and watch the first slew.
Next step
Once you know what the ground can carry, browse crane rental to compare capacities and request a quote, or message us on WhatsApp with the load, the radius and photos of the set-up point.
Sources and scope
Each source supports the topic described below, not every statement in this article. Foreign guidance does not replace Egyptian requirements or site rules. Use the manual matching the machine model and serial number for operation.
- OSHA 29 CFR 1926.1402 — Ground conditions (cranes and derricks in construction)
Ground must be firm, drained and graded, with supporting materials such as mats or cribbing where needed; the controlling entity provides ground preparation and tells the crane user about voids, tanks and utilities under the set-up area. US crane rule, not Egyptian law.
- CPA CIG 2308 — Guidance on the Supply, Management and Operation of Mobile Cranes (V2, May 2026)
The crane supplier provides outrigger loadings; the crane user stays responsible for assessing and preparing the ground and may ask for larger pads; outrigger point loads for a 360-degree slew and mat material, size, capacity and weight belong in the supply information. UK industry guidance, not Egyptian law.
- HSE — Planning lifting operations
Competent lift planning and supervision. UK guidance, not a statement of Egyptian law.
Need a machine for your site?
Browse EXON's maintained fleet or talk to the team for a project quote.
Keep reading
Sling Angle Load Calculation: How Much Each Leg Really Carries
Sling angle load calculation for site lifts: why a 4-tonne load can put 4 tonnes on each leg, the L ÷ H method, worked examples and when to retire a sling.
Excavation Slope Angle by Soil Type: How Far Back to Cut the Sides
Excavation slope angle by soil type: 53°, 45° and 34° from the OSHA table, how to work out the top width and extra volume, and when to support the sides.
Safe Distance From Power Lines for Cranes and Excavators: Clearances by Voltage
Safe distance from power lines for cranes, excavators and tippers: clearance by voltage in metres, the 6 m planning zone, spotters and what to do after contact.